Centrale termoelettrica di Ravenna - Sostituzione del ciclo combinato TG-501 con nuovi turbogeneratori TG - Capacity Strategy Italia


General information

Work: Co-generation plant in Ravenna

Project: Centrale termoelettrica di Ravenna - Sostituzione del ciclo combinato TG-501 con nuovi turbogeneratori TG - Capacity Strategy Italia

Developer: Enipower S.p.A.

Project type: Thermal power plant

Deadline for submission of comments: 23/12/2019 mail

Other projects related to the same work: Show / Hide

Territories and marine areas

Regions: Emilia Romagna

Provinces: Ravenna

Municipalities: Ravenna

Marine areas: None

Select procedure

Procedure Procedure Code Starting date Stage of the procedure
Environmental Impact Assessment 4940 15/10/2019 EIA-SEA Technical Committee's assessment Procedure details Documents