Unsubstantial project changes (Strategic works Law 443/2001) |
7523 |
18/10/2021 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
7523 |
Subject
: |
Nuova S.S. 341 "Gallaratese" tratto da Samarate al confine con la provincia di Novara (tratto Nord). Stralcio funzionale dal km 6+500 (Svincolo 336 Nord) al km 8+844 (Svincolo autostrada A8) c.d. Bretella di Gallarate |
Date of application submission: |
18/10/2021 |
Date of request for documents perfection : |
04/11/2021 |
Date of perfection proceedings documents receipt: |
10/11/2021 |
Technical assessment starting date: |
12/11/2021 |
Date of the Opinion of the National Technical Commission : |
22/12/2021 |
National Technical Commission Opinion number: |
201 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the EIA Decree: |
11/01/2022 |
EIA Decree number: |
MiTE_DEC_2022-0000007 |
EIA Decree outcome: |
Positivo con prescrizioni |
Notification date: |
14/01/2022 |
Notification Reference number: |
MiTE_2022-0004162 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Follow-up (Strategic works Law 443/2001) |
7363 |
30/08/2021 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
7363 |
Subject
: |
Nuova S.S. 341 "Gallaratese, tratto da Samarate a confine con la Provincia di Novara (Tratto Nord), Stralcio Funzionale dal km 6+500 (Svincolo 336 Nord) al km 8+844 (Svincolo Autostrada A8) c.d. Bretella di Gallarate. Progetto Esecutivo. |
Date of application submission: |
30/08/2021 |
Date of request for documents perfection : |
27/07/2022 |
Date of the Opinion of the National Technical Commission - Stage 1: Adequacy of the executive project to the final project and compliance to the prescriptions: |
30/12/2021 |
National Technical Commission Opinion number - Stage 1: |
405 |
National Technical Commission Opinion outcome - Stage 1: |
Emanato parte negativo più parziale positivo con prscrizioni |
Determination date - Stage 1: Adequacy of the executive project to the final project and prescriptions compliance : |
19/01/2022 |
Determination number - Stage 1 : |
MiTE_DEC_2022-0000013 |
Determination outcome - Stage 1: |
Emanato parte negativo più parziale positivo con prscrizioni |
Date of the Opinion of the National Technical Commission - Stage 2: environmental monitoring and prescriptions compliance : |
25/09/2023 |
National Technical Commission Opinion number - Stage 2: |
837 |
National Technical Commission Opinion outcome - Stage 2: |
Positivo |
Determination date - Stage 2: environmental monitoring and prescriptions compliance : |
20/10/2023 |
Determination number - Stage 2 : |
MASE_VA_DEC_2023-0000492 |
Determination outcome - Stage 2: |
Positivo |
Notification date: |
27/10/2023 |
Notification Reference number: |
MASE_2023-0173153 |
Responsible of the procedure: |
Carlo Di Gianfrancesco - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|
Environmental Impact Assessment (Strategic works Law 443/2001) |
1711 |
15/12/2011 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
1711 |
Subject
: |
Variante della bretella di Gallarate tra il km 7+348 al km 8+843 e Verifica di ottemperanza sul tratto stradale tra il km 0+000 ed il km 7+348 |
Date of application submission: |
15/12/2011 |
Date of request for documents perfection : |
29/02/2012 |
Technical assessment starting date: |
18/07/2012 |
Date of the Opinion of the National Technical Commission : |
25/01/2013 |
National Technical Commission Opinion number: |
1155 |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
07/02/2013 |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment (Strategic works Law 443/2001) |
614 |
16/12/2003 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
614 |
Date of application submission: |
16/12/2003 |
Publication date of the notice in newspapers: |
10/12/2003 |
Deadline of submission of Public Comments: |
09/01/2004 |
Technical assessment starting date: |
28/10/2004 |
Date of request for integrations: |
26/11/2004 |
Date of integrations receipt: |
04/04/2005 |
Date of Special EIA Commission Opinion: |
06/09/2005 |
Special EIA Commission Opinion outcome: |
Positivo con prescrizioni |
Date of the communication of the Opinion to the Ministry of Infrastructures and Transports : |
06/10/2005 |
Date of CIPE Deliberation: |
01/08/2008 |
CIPE Deliberation number : |
79 |
CIPE Deliberation outcome: |
Positivo con prescrizioni |
Publication date of CIPE Deliberation in the Italian Republic Official Journal : |
15/04/2009 |
Italian Republic Official Journal number : |
50 |
Stage of the Procedure: |
Concluded |