Subject
: |
Realizzazione di un impianto di stoccaggio Gas "Bordolano Stoccaggio" in comune di Bordolano (CR) - Prescrizioni: A8, A9, C7 |
Date of application submission: |
17/04/2023 |
Technical assessment starting date: |
25/05/2023 |
Determination date: |
25/01/2024 |
Determination number: |
MASE_VA_DEC_2024-0000029 |
Determination outcome: |
Ottemperata |
Responsible of the procedure: |
Orsola Renata Reillo - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
6106 |
06/04/2021 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
6106 |
Subject
: |
Realizzazione di un impianto di stoccaggio Gas "Bordolano Stoccaggio" in comune di Bordolano (CR) - Prescrizione: A9 |
Date of application submission: |
06/04/2021 |
Date of the Opinion of the National Technical Commission : |
25/06/2021 |
National Technical Commission Opinion number: |
288 |
National Technical Commission Opinion outcome: |
Parzialmente Ottemperata |
Determination date: |
31/05/2022 |
Determination number: |
MiTE_VA_DEC_2022-0000081 |
Determination outcome: |
Ottemperata |
Notification date: |
08/06/2022 |
Notification Reference number: |
MiTE_2022-0071220 |
Stage of the Procedure: |
Concluded |
EIA Compliance |
6105 |
06/04/2021 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
6105 |
Subject
: |
Realizzazione di un impianto di stoccaggio Gas "Bordolano Stoccaggio" in comune di Bordolano (CR) - Prescrizione: A8 |
Date of application submission: |
06/04/2021 |
Date of EIA Commission Opinion : |
25/06/2021 |
EIA Commission Opinion number: |
288 |
EIA Commission Opinion outcome: |
Parzialmente Ottemperata |
Determination date: |
31/05/2022 |
Determination number: |
MiTE_VA_DEC_2022-0000080 |
Determination outcome: |
Ottemperata |
Notification date: |
06/06/2022 |
Notification Reference number: |
MiTE_2022-0070386 |
Stage of the Procedure: |
Concluded |
EIA Compliance |
4753 |
25/06/2019 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4753 |
Subject
: |
Realizzazione di un impianto di stoccaggio Gas "Bordolano Stoccaggio" in comune di Bordolano (CR) - Prescrizione: A9 |
Date of application submission: |
25/06/2019 |
Technical assessment starting date: |
01/07/2019 |
Date of the Opinion of the National Technical Commission : |
13/02/2020 |
National Technical Commission Opinion number: |
3273 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
17/04/2020 |
Determination number: |
50 |
Determination outcome: |
Ottemperata |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
4752 |
25/06/2019 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4752 |
Subject
: |
Realizzazione di un impianto di stoccaggio Gas "Bordolano Stoccaggio" in comune di Bordolano (CR) - Prescrizione: A8 |
Date of application submission: |
25/06/2019 |
Technical assessment starting date: |
01/07/2019 |
Date of the Opinion of the National Technical Commission : |
13/02/2020 |
National Technical Commission Opinion number: |
3273 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
17/04/2020 |
Determination number: |
52 |
Determination outcome: |
Ottemperata |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
4194 |
13/04/2017 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
4194 |
Subject
: |
Nuova centrale gas Bordolano - Modifiche all'assetto impiantistico ed alla disposizione delle apparecchiatuare e fabbricati degli impianti di compressione e di trattamento. - Prescrizione: 1 |
Date of application submission: |
13/04/2017 |
Date of notification to the developer of the procedure outcomes: |
22/03/2019 |
Date of the Opinion of the National Technical Commission : |
14/12/2018 |
National Technical Commission Opinion number: |
PRR CTVIA 2901 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
22/02/2019 |
Determination number: |
DVA-DEC-0000054 |
Determination outcome: |
Ottemperata |
Notification Reference number: |
DVA_2019-0007396 |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
3671 |
13/04/2017 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3671 |
Subject
: |
Prescrizione A8 del Decreto VIA n. 1633 del 12/11/2009 |
Date of application submission: |
13/04/2017 |
Date of notification to the developer of the procedure outcomes: |
22/03/2019 |
Date of integrations receipt: |
04/07/2018 |
Date of the Opinion of the National Technical Commission : |
14/12/2019 |
National Technical Commission Opinion number: |
2901 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
22/02/2019 |
Determination number: |
DVA-DEC-2019-0000054 |
Determination outcome: |
Ottemperata |
Notification Reference number: |
DVA_2019-0007396 |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
3843 |
17/05/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3843 |
Subject
: |
Prescrizione A9 del Decreto VIA n. 1633 del 12/11/2009 |
Date of application submission: |
17/05/2016 |
Date of integrations receipt: |
13/04/2017 |
Date of notification to the developer of the procedure outcomes: |
24/06/2019 |
Date of integrations second receipt: |
04/07/2018 |
Date of the Opinion of the National Technical Commission : |
10/05/2019 |
National Technical Commission Opinion number: |
3001 |
National Technical Commission Opinion outcome: |
ottemperata |
Determination date: |
17/06/2019 |
Determination number: |
DVA_DEC_2019-0000209 |
Determination outcome: |
Ottemperata |
Notification Reference number: |
DVA_2019-0016038 |
Outcome: |
Ottemperata |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
3364 |
04/03/2016 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3364 |
Subject
: |
Prescrizioni A1, A10, A2, A3, A5, A6, A8 e A9 del Decreto VIA n. 1633 del 12/11/2009 |
Date of application submission: |
04/03/2016 |
Technical assessment starting date: |
03/05/2017 |
Date of integrations receipt: |
13/04/2017 |
Determination date: |
18/12/2017 |
Determination number: |
DVA-2017-0029349 |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
EIA Compliance |
3175 |
05/11/2015 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3175 |
Subject
: |
Prescrizione A7 del Decreto VIA n. 1633 del 12/11/2009 |
Date of application submission: |
05/11/2015 |
Technical assessment starting date: |
09/11/2015 |
Date of the Opinion of the National Technical Commission : |
04/12/2015 |
National Technical Commission Opinion number: |
1932 |
National Technical Commission Opinion outcome: |
Ottemperata |
Determination date: |
17/12/2015 |
Determination number: |
DVADEC-2015-0000473 |
Determination outcome: |
Ottemperata |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225071 - 0657225070 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |
Environmental Impact Assessment |
266 |
11/07/2008 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
266 |
Date of application submission: |
11/07/2008 |
Publication date of the notice in newspapers: |
07/07/2008 |
Deadline of submission of Public Comments: |
05/09/2008 |
Technical assessment starting date: |
24/07/2008 |
Date of the EIA Decree: |
12/11/2009 |
EIA Decree number: |
1633 |
EIA Decree outcome: |
Positivo con prescrizioni |
Stage of the Procedure: |
Concluded |