Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

Centrale Termoelettrica di Leinì

General information

Installation: Centrale Termoelettrica di Leinì

Localization: 10040 - SP 3 (Cebrosa) K. 5,100

Installation type: Thermal power plant

Activity type: 1.1 - Impianti di combustione con potenza calorifica di combustione > 50 MW; 

Operator: ENGIE Produzione S.p.A.

Tax code: 02019870696

Installation status: Installazione in esercizio

Territories and marine areas

Regions: Piemonte

Provinces: Torino

Municipalities: Leini'

Marine areas: None

Select procedure

Procedure Procedure Code Starting date Stage of the procedure
IPPC permit for non substantial changes 182/12874 23/05/2022 Concluded Procedure details Documents
IPPC permit for non substantial changes 182/11035 21/10/2020 Concluded Procedure details Documents
IPPC permit’s reconsideration 182/10173 06/05/2019 Concluded Procedure details Documents
IPPC permit for non substantial changes 182/10016 26/02/2019 Concluded Procedure details Documents
IPPC permit for non substantial changes 182/743 05/05/2014 Concluded Procedure details Documents
IPPC permit’s renewal 182 06/03/2009 Concluded Procedure details Documents