Work: Natural gas pipeline Chieti-San Salvo
Project: Variant for PIDI insertion n. 18.2 on the Chieti-San Salvo natural gas DN 550 (22 ") MOP 70 bar pipeline and related works
Description: The project involves the construction of a new 18.2 PIDI plant (point of interception and important derivation) in the Chieti-San Salvo natural gas DN 550 (22 ") MOP 70 bar pipeline. The laying of about 1.3 km of pipelines and the discharging of about 3.6 km of pipelines is also planned.
Developer: SNAM RETE GAS S.p.A.
Project type: Natural gas pipelines
Regions: Abruzzo
Provinces: Chieti
Municipalities: Paglieta, Torino di Sangro
Marine areas: None
Procedure | Procedure Code | Starting date | Stage of the procedure | ||
---|---|---|---|---|---|
EIA Compliance | 5061 | 13/12/2019 | Concluded | Procedure details | Documents |
EIA Screening | 4145 | 25/06/2018 | Concluded | Procedure details | Documents |