Reconstruction of the Ravenna - Chieti natural gas pipeline from San Benedetto del Tronto to Chieti
General information
Work: Natural gas pipeline Ravenna-Chieti
Project: Reconstruction of the Ravenna - Chieti natural gas pipeline from San Benedetto del Tronto to Chieti
Description: The project involves the construction of the new natural gas pipeline to replace the existing from San Benedetto del Tronto to Chieti DN 650 (26 ") 75.970 km long and the construction of 26 new secondary pipelines 14.770 km long and the decommissioning of the existing pipeline (74.070 km) and existing secondary lines (10.905 km).
Developer: SNAM RETE GAS S.p.A.
Project type: Natural gas pipelines
Deadline for submission of comments: 28/02/2021
mail
Other projects related to the same work: Show / Hide
Project |
Developer |
Procedure |
Info |
Doc |
Reconstruction of the Ravenna - Chieti natural gas pipeline from Recanati to San Benedetto del Tronto |
SNAM RETE GAS S.p.A. |
Environmental Impact Assessment |
Info Project and procedures
|
documents
|
Reconstruction of Ravenna-Chieti natural gas pipeline, Ravenna-Jesi section and related works |
SNAM RETE GAS S.p.A. |
Environmental Impact Assessment |
Info Project and procedures
|
documents
|
Territories and marine areas
Regions: Marche, Abruzzo
Provinces: Chieti, Pescara, Teramo, Ascoli Piceno
Municipalities: Moscufo, Giulianova, Martinsicuro, Mosciano Sant'Angelo, San Benedetto del Tronto, Silvi, Roseto degli Abruzzi, Atri, Pineto, Chieti, Cepagatti, Monteprandone, Spoltore, Colonnella, Collecorvino, Tortoreto, Citta' Sant'Angelo, Pianella, Cappelle sul Tavo, Alba Adriatica
Marine areas: None
Select procedure
Procedure |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment |
3832 |
30/11/2017 |
EIA-SEA Technical Committee's assessment
|
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3832 |
Date of application submission: |
30/11/2017 |
Data avvio consultazione pubblica: |
12/12/2017 |
Deadline of submission of Public Comments: |
10/02/2018 |
Technical assessment starting date: |
12/12/2017 |
Date of request for integrations: |
30/07/2018 |
Date of integrations receipt: |
26/02/2019 |
Data ripubblicazione avviso sul sito web e avvio consultazione pubblica: |
23/05/2019 |
Deadline of submission of Public Comments on the republished project: |
22/06/2019 |
Second Republication date of the notice: |
29/01/2021 |
Deadline of submission of Public Comments - Second republication: |
28/02/2021 |
Ministry of Cultural Heritage and Tourism Opinion date: |
16/06/2020 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
45260 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
Positivo con prescrizioni/raccomandazioni |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225903 - cress-5@minambiente.it |
Stage of the Procedure: |
EIA-SEA Technical Committee's assessment
|