Methane supply network in Sardinia - Northern section
General information
Work: Methane supply network in Sardinia
Project: Methane supply network in Sardinia - Northern section
Description: The project involves the installation of the DN 650 (26") gas pipeline from Palmas Arborea to Porto Torres 126,495 km long, and of a DN 400 (16") gas pipeline from Macomer to Olbia, of 104,480 km long and of sencondary pipes functionally connected to the main lines of the length of about 110 km.
Developer: SNAM RETE GAS S.p.A.
Project type: Natural gas pipelines
Deadline for submission of comments: 02/06/2019
mail
Other projects related to the same work: Show / Hide
Territories and marine areas
Regions: Sardegna
Provinces: Sassari, Nuoro, Oristano
Municipalities: Noragugume, Semestene, Ottana, Torralba, Mara, Uri, Ittiri, Orani, Mores, Thiesi, Oristano, Borutta, Suni, Olmedo, Oniferi, Dualchi, Macomer, Villaurbana, Olbia, Bonorva, Zerfaliu, Abbasanta, Ozieri, Sindia, Oschiri, Nuoro, Simaxis, Alghero, Pozzomaggiore, Porto Torres, Sassari, Romana, Borore, Paulilatino, Palmas Arborea, Monti, Berchidda, Siamanna, Norbello, Ollastra, Loiri Porto San Paolo, Cossoine, Bolotana, Villanova Truschedu
Marine areas: None
Select procedure
Procedure |
Procedure Code |
Starting date |
Stage of the procedure |
|
|
Environmental Impact Assessment |
3673 |
26/07/2017 |
Concluded |
Procedure details
|
Documents
|
Procedure Code (ID_VIP/ID_MATTM) |
3673 |
EIA-AA integrated Procedure : |
Sì |
Subject
: |
Metanizzazione Sardegna - tratto Nord |
Date of application submission: |
26/07/2017 |
Data avvio consultazione pubblica: |
03/08/2017 |
Deadline of submission of Public Comments: |
02/10/2017 |
Technical assessment starting date: |
17/08/2017 |
Date of request for integrations: |
17/01/2018 |
Date of integrations receipt: |
16/05/2018 |
Republication date of the notice: |
20/06/2018 |
Deadline of submission of Public Comments on the republished project: |
20/07/2018 |
Date of integrations related to the republished project receipt: |
06/09/2018 |
Second Republication date: |
03/05/2019 |
Deadline of submission of Public Comments - Second republication: |
02/06/2019 |
Date of the Opinion of the National Technical Commission : |
10/01/2020 |
National Technical Commission Opinion number: |
3243 |
National Technical Commission Opinion outcome: |
Positivo con prescrizioni |
Ministry of Cultural Heritage and Tourism Opinion date: |
25/10/2019 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
30477 |
Ministry of Cultural Heritage and Activities and Tourism Opinion date: |
Positivo |
Date of the EIA Decree: |
05/12/2022 |
EIA Decree number: |
DM_2022-0000373 |
EIA Decree outcome: |
Positivo |
Notification date: |
06/12/2022 |
Notification Reference number: |
MiTE-2022-0153091 |
Notes: |
L'avviso al pubblico del 20/06/2018 relativo alla ripubblicazione riporta erroneamente il riferimento normativo all'art. 24, c.3 del D.Lgs 152/2006 per i tempi di consultazione, il corretto riferimento normativo relativo ai termini della consultazione pubblica in caso di ripubblicazione è l'art.24, c5. del D.Lgs 152/2006 |
Responsible of the procedure: |
Carmela Bilanzone - tel. 0657225074 - va-5@mite.gov.it |
Stage of the Procedure: |
Concluded |