Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

Remake of the 150 kV power line Corato-Bari Industriale 2 in the municipalities of Corato, Ruvo di Puglia, Terlizzi, Bitonto and Modugno in the Province of Bari


General information

Work: 150 kV power line Corato-Bari

Project: Remake of the 150 kV power line Corato-Bari Industriale 2 in the municipalities of Corato, Ruvo di Puglia, Terlizzi, Bitonto and Modugno in the Province of Bari

Description: The project involves the construction of the new 36 km long 150 kV overhead power line between the electrical substation of Bari Industriale 2, located in the industrial area of Modugno, and the electrical substation of Corato and the disposal of the existing 150 kV TERNA power line. The main purposes of the project are to decrease interference with the urbanized areas and to minimize the impacts on local populations.

Developer: Terna Rete Italia S.p.A.

Project type: Electrical power lines

Deadline for submission of comments: 02/04/2018 mail

Territories and marine areas

Map

Regions: Puglia

Provinces: Bari

Municipalities: Bitonto, Terlizzi, Modugno, Corato, Ruvo di Puglia

Marine areas: None

Select procedure

Procedure Procedure Code Starting date Stage of the procedure
Environmental Impact Assessment 2811 06/08/2014 Concluded Procedure details Documents