Work: Thermal power plant of Brindisi Nord
Project: North Brindisi thermal power plant - Divestiture of the units 1-2 and of 220 kV electricity substation
Description: The project involves the demolition of the groups 1 and 2 (boilers, electrostatic precipitators, flue-gas ducks and chimney) and of the 220 kV section of the electrical station of North Brindisi power plant. Infrastructure such as roads, squares, sewers and underground utilities will be kept active for the operation of groups 3 and 4, which will remain in service.
Developer: EDIPOWER S.p.A.
Project type: Thermal power plant
Deadline for submission of comments: 14/06/2014 mail
Other projects related to the same work: Show / Hide
Regions: Puglia
Provinces: Brindisi
Municipalities: Brindisi
Marine areas: None
Procedure | Procedure Code | Starting date | Stage of the procedure | ||
---|---|---|---|---|---|
EIA Screening | 2720 | 15/04/2014 | Concluded | Procedure details | Documents |