Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

New electrical substation 380/150 kV of Vizzini, overhead 380/150 kV connections to the National Transmission Grid and related works


General information

Work: New electrical substation 380/150 kV of Vizzini, overhead 380/150 kV connections to the National Transmission Grid and related works

Project: New electrical substation 380/150 kV of Vizzini, overhead 380/150 kV connections to the National Transmission Grid and related works

Description: The project involves the construction of the new Vizzini 380/150 kV electrical substation, the 380 kV and 150 kV overhead single circuit connections to the electrical substation of Vizzini, the 150 kV overhead power line between the electrical substations of Vizzini and Licodia Eubea, the construction of 150 kV overhead power line from the Vizzini substation to the existing Primary substation of Mineo and the demolition of 7,2 km of existing power lines.

Developer: Terna Rete Italia S.p.A.

Project type: Electrical power lines

Other projects related to the same work: Show / Hide

Territories and marine areas

Map

Regions: Sicilia

Provinces: Catania

Municipalities: Mineo, Militello in Val di Catania, Vizzini, Licodia Eubea

Marine areas: None

Select procedure

Procedure Procedure Code Starting date Stage of the procedure
Environmental Impact Assessment 10656 07/12/2023 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Compliance 9050 07/11/2022 Concluded Procedure details Documents
EIA Compliance 9047 13/10/2022 Concluded Procedure details Documents
EIA Compliance 9331 12/10/2022 Concluded Procedure details Documents
EIA Compliance 8922 27/09/2022 Concluded Procedure details Documents
EIA Compliance 8924 22/09/2022 Concluded Procedure details Documents
EIA Compliance 8894 08/09/2022 EIA-SEA Technical Committee's assessment Procedure details
Environmental Impact Assessment 8857 07/09/2022 Approved with/without prescriptions Procedure details Documents
Environmental Impact Assessment 8882 30/06/2022 Approved with/without prescriptions Procedure details Documents
EIA Compliance 8417 16/05/2022 Concluded Procedure details Documents
EIA Compliance 8379 05/05/2022 Concluded Procedure details Documents
EIA Compliance 8364 04/05/2022 Concluded Procedure details Documents
EIA Compliance 8363 02/05/2022 Administrative control Procedure details Documents
EIA Compliance 8347 06/04/2022 Concluded Procedure details Documents
Environmental Impact Assessment 8193 23/03/2022 Approved with/without prescriptions Procedure details Documents
EIA Compliance 7344 20/12/2021 Concluded Procedure details Documents
EIA Compliance 7470 18/10/2021 Concluded Procedure details Documents
EIA Compliance 5391 04/10/2021 Concluded Procedure details Documents
EIA Compliance 7466 27/09/2021 Concluded Procedure details Documents
EIA Compliance 7458 21/09/2021 Concluded Procedure details Documents
EIA Compliance 7402 15/09/2021 Concluded Procedure details Documents
EIA Compliance 6280 02/08/2021 Concluded Procedure details Documents
EIA Compliance 7316 28/07/2021 Concluded Procedure details Documents
EIA Compliance 5627 29/10/2020 Concluded Procedure details Documents
EIA Compliance 5335 20/10/2020 Concluded Procedure details Documents
EIA Compliance 5392 17/06/2020 Concluded Procedure details Documents
EIA Compliance 4963 07/04/2020 Concluded Procedure details Documents
EIA Compliance 4543 16/05/2019 Concluded Procedure details Documents
Environmental Impact Assessment 2568 24/10/2013 Concluded Procedure details Documents