Environmental Assessments and Authorizations: SEA - EIA - IPPC Permit

You are in:

New rail link between Lyon and Turin - French-Italian common section - Italian section from the border to Susa-Bussoleno


General information

Work: Turin-Lyon high-speed railway

Project: New rail link between Lyon and Turin - French-Italian common section - Italian section from the border to Susa-Bussoleno

Description: The rail section runs from the east entrance of the Base Tunnel to the junction with the historic line Turin-Modane before the Bussoleno railway station. The project subject to environmental impact assessment (EIA) involves location variants to: the Plain of Susa, storage sites of Caprie and Torazza Piemonte, the ventilation stations of Maddalena and Clarea, the conduit between Venaus and Susa, other works pertaining to the manager of the A32 motorway.

Developer: Lyon Turin Ferroviaire

Project type: Railways

Other projects related to the same work: Show / Hide

Territories and marine areas

Map

Regions: Piemonte

Provinces: Torino

Municipalities: Susa, Giaglione, Condove, Venaus, Mattie, Bussoleno, Chiomonte, Mompantero, Chiusa di San Michele, Torrazza Piemonte, Caprie

Marine areas: None

Select procedure

Procedure Procedure Code Starting date Stage of the procedure
EIA Follow-up (Strategic works Law 443/2001) 5029 09/12/2019 EIA-SEA Technical Committee's assessment Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 4464 21/01/2019 Pending the start of the enivronmental monitoring Procedure details Documents
EIA Follow-up (Strategic works Law 443/2001) 4193 31/07/2018 Pending the start of the enivronmental monitoring Procedure details Documents
Environmental Impact Assessment (Strategic works Law 443/2001) 3656 11/07/2017 Concluded Procedure details Documents
Environmental Impact Assessment (Strategic works Law 443/2001) 2312 19/04/2013 Concluded Procedure details Documents
EIA Compliance (Strategic works Law 443/2001) 2313 17/04/2013 Concluded Procedure details Documents